TNPRC Building 2 - Week of September 13, 2019

Sources of Noise

  • Hand Tools

Utility Shutdowns

  • None currently.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Complete wall MEP rough-in.
  • Begin hanging drywall. 
  • Continue domestic water tie in.
  • Apply spray foam insulation to exterior walls.
  • Commissioning agent inspection.

Recap of week ending September 12, 2019

  • Passed partial electrical and plumbing Parish inspections.
  • Began hanging VAV boxes, dampers, and continued hanging ducts.
  • Cut roof penetrations, installed curbs, and mounted 2 roof exhaust units.
  • Began insulating pipes, continued domestic water tie in and floor cores. 
  • Continued hanging pipe for the fire sprinkler system.