TNPRC Building 2 - Week of October 18, 2019

Sources of Noise

  • Hand Tools

Utility Shutdowns

  • None currently.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Perform ground penetrating survey to prep for crane placement.
  • Lift mechanical equipment to roof.
  • Tape and float drywall.  
  • Skim and prep ceiling. 
  • Continue chilled water and steam lines.
  • Electrical rough-in ongoing.  
  • ACM panel exterior hat channel progressing.

Recap of week ending October 17, 2019

  • Began taping and floating drywall.  Continued installing Drywall.
  • Hat channel installation for Architectural Panels moving forward.
  • Crawlspace chilled water and steam line installation ongoing.
  • Continued installing Penthouse electrical panels and conduits.
  • Duct installation advancing.
  • Continued skimming and prepping ceiling.