Sources of Noise
- Hand Tools
Utility Shutdowns
- None currently.
Deliveries
- Materials and equipment.
Events for upcoming week
- Penthouse electrical rough-in ongoing.
- Begin taping and floating.
- Continue hanging drywall.
- Continue skimming and prepping ceiling.
- Crawlspace chilled water and steam lines advancing.
- Hat channel for Architectural panels ongoing.
Recap of week ending October 10, 2019
- Crawlspace chilled water and steam line installation ongoing.
- Continued installing Penthouse electrical panels and conduits.
- Weather barrier application finalized.
- Completed hanging VAV boxes and installing fire dampers.
- Fire system riser assembly installed.
- Resumed skimming and prepping ceiling.