Sources of Noise
- Hand Tools
Utility Shutdowns
- Electrical panel DPB3 and DP4
Deliveries
- Materials and equipment.
Events for upcoming week
- Begin installing roof top chill and steam lines.
- Verify electrical circuits. Swap circuits from old panels to new panels.
- Install control circuits for new HVAC system.
- Continue taping, floating, and sanding drywall. Skim and prep ceiling.
- Rough-in power to VFD’s ongoing. Continue pulling circuits.
Recap of week ending November 7, 2019
- Installed shut off valves to the existing chill, steam, and condensate lines.
- Began installing chill and steam roof pipe supports.
- Duct pressure tested for leaks.
- Panel mock-up has been reviewed by Architect with adjustments required.
- Taping, floating, and sanding drywall ongoing.
- Penthouse electrical rough-in and pulling circuits ongoing.
- Continued ceiling skim and prep.