TNPRC Building 2 - Week of November 8, 2019

Sources of Noise

  • Hand Tools

Utility Shutdowns

  • Electrical panel DPB3 and DP4

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Begin installing roof top chill and steam lines.
  • Verify electrical circuits.  Swap circuits from old panels to new panels.
  • Install control circuits for new HVAC system.
  • Continue taping, floating, and sanding drywall.  Skim and prep ceiling. 
  • Rough-in power to VFD’s ongoing.  Continue pulling circuits.  

Recap of week ending November 7, 2019

  • Installed shut off valves to the existing chill, steam, and condensate lines.
  • Began installing chill and steam roof pipe supports.
  • Duct pressure tested for leaks.
  • Panel mock-up has been reviewed by Architect with adjustments required.
  • Taping, floating, and sanding drywall ongoing.  
  • Penthouse electrical rough-in and pulling circuits ongoing.
  • Continued ceiling skim and prep.