Sources of Noise
- Hand Tools
Utility Shutdowns
- Electrical panel DPB3 and DP4
Deliveries
- Materials and equipment.
Events for upcoming week
- AHU and heat exchanger lift scheduled for Wednesday.
- Verify electrical circuits. Swap circuits from old panels to new panels.
- Skim and prep ceiling. Continue taping, floating, and sanding drywall.
- Continue electrical rough in, pulling circuits, and installing conduit.
Recap of week ending November 14, 2019
- Began installing roof top chill and steam lines. Started plumbing AHU.
- Started installing control circuits for new HVAC system.
- Taping, floating, and sanding drywall continues. Began priming ceiling.
- Penthouse electrical rough-in and pulling circuits progressing.
- Continued ceiling skim and prep.