TNPRC Building 2 - Week of November 15, 2019

Sources of Noise

  • Hand Tools

Utility Shutdowns

  • Electrical panel DPB3 and DP4

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • AHU and heat exchanger lift scheduled for Wednesday.
  • Verify electrical circuits.  Swap circuits from old panels to new panels.
  • Skim and prep ceiling.  Continue taping, floating, and sanding drywall.  
  • Continue electrical rough in, pulling circuits, and installing conduit. 

Recap of week ending November 14, 2019

  • Began installing roof top chill and steam lines.  Started plumbing AHU.
  • Started installing control circuits for new HVAC system.
  • Taping, floating, and sanding drywall continues.  Began priming ceiling.
  • Penthouse electrical rough-in and pulling circuits progressing.
  • Continued ceiling skim and prep.