TNPRC Building 2 - Week of July 5, 2019

Sources of Noise

  • Hand Tools
  • Scarify and chip concrete floor.

Utility Shutdowns

  • None at this time.

Deliveries

  • Materials and equipment.

Events for upcoming week

  • Histology mechanical and plumbing revisions ongoing.  
  • Continue to remove AHU#5.
  • Begin removing two courtyard Pine Trees.
  • Continue chipping and scarifying existing concrete floors.
  • Relocate circuits from panel B-20 to panel B-21.

Recap of week ending July 4, 2019

  • Poured concrete curb, existing drains, and bathroom floors.
  • Began removing AHU#5 and ducts. 
  • Continued removing roof top units and discarding.
  • Resumed hanging crawlspace data conduits.