Sources of Noise
- Hand Tools
Utility Shutdowns
- None at this time.
Deliveries
- Materials and equipment.
Events for upcoming week
- Relocate circuits from panel B-20 to panel B-21. Continue data conduits.
- Histology mechanical, plumbing, and ceiling revisions ongoing.
- Install a water main valve for Building 2. Cap two small water lines.
- Continue to remove AHU#5 and associated ducting.
- Continue removing two courtyard Pine Trees.
- Continue patching floors. Begin wall layout.
Recap of week ending July 11, 2019
- Wrecked curb forms, infilled duck penetrations, re-routed electrical circuits, removed existing duct, and began relocating VAV boxes above the Histology Lab.
- Cut rough opening and currently framing new door into the Histology Lab.
- Began vacuuming the scarified floor and began patching.
- Continued removing AHU#5, associated ducts, and roof top exhaust units.
- Continued hanging crawlspace data conduits.