TNPRC Building 2 - Week of July 12, 2019

Sources of Noise

  • Hand Tools

Utility Shutdowns

  • None at this time.

Deliveries
 

  • Materials and equipment.

Events for upcoming week

  • Relocate circuits from panel B-20 to panel B-21.  Continue data conduits.
  • Histology mechanical, plumbing, and ceiling revisions ongoing. 
  • Install a water main valve for Building 2.  Cap two small water lines.   
  • Continue to remove AHU#5 and associated ducting.
  • Continue removing two courtyard Pine Trees.
  • Continue patching floors.  Begin wall layout. 

Recap of week ending July 11, 2019
    

  • Wrecked curb forms, infilled duck penetrations, re-routed electrical circuits, removed existing duct, and began relocating VAV boxes above the Histology Lab. 
  • Cut rough opening and currently framing new door into the Histology Lab.
  • Began vacuuming the scarified floor and began patching.
  • Continued removing AHU#5, associated ducts, and roof top exhaust units.
  • Continued hanging crawlspace data conduits.