Sources of Noise
- Hand Tools
Utility Shutdowns
- None at this time.
Deliveries
- Materials and equipment.
Events for upcoming week
- AHU 3 demolition. Reroute chill water to existing mini split.
- Continue pulling circuits and making panels. Energize new lights.
- Continue skimming, sanding, and applying finishes.
- Lab casework installation moving forward.
- Exterior ACM Panels ongoing. Continue exterior glazing.
- Begin leveling subfloor and install flooring.
Recap of week ending January 16, 2019
- Electricians swapped Building A-19 and Building A-1 circuits to new panels. Continued making up panels, installing lights, pulling circuits, and hanging crawlspace conduit. Torque tested electrical panels.
- Began rerouting chill water lines to existing mini split system.
- Installed (4) doors and removed (2) partition walls in the occupied hall.
- Resumed casework installation. Drywall and frame finish ongoing.
- Completed ceiling grid, hanging drywall, and fur down.
- Began courtyard exterior glazing. Continued ACM panels.