TNPRC Building 2 - Week of January 17, 2020

Sources of Noise

  • Hand Tools

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • AHU 3 demolition.  Reroute chill water to existing mini split.
  • Continue pulling circuits and making panels. Energize new lights.
  • Continue skimming, sanding, and applying finishes.  
  • Lab casework installation moving forward.
  • Exterior ACM Panels ongoing.  Continue exterior glazing.
  • Begin leveling subfloor and install flooring.

Recap of week ending January 16, 2019

  • Electricians swapped Building A-19 and Building A-1 circuits to new panels.  Continued making up panels, installing lights, pulling circuits, and hanging crawlspace conduit.  Torque tested electrical panels. 
  • Began rerouting chill water lines to existing mini split system. 
  • Installed (4) doors and removed (2) partition walls in the occupied hall.             
  • Resumed casework installation.  Drywall and frame finish ongoing.  
  • Completed ceiling grid, hanging drywall, and fur down.
  • Began courtyard exterior glazing.  Continued ACM panels.