TNPRC Breeding Colony Expansion - Week of Novermber 19, 2021

Sources of Noise

  • Excavation equipment.
  • Hand Tools.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Begin concrete prep for field enclosure one perimeter.
  • Lixit water installation at field enclosure one ongoing.
  • Continue welding horizonal rails at enclosure one.
  • Currently stretching enclosure one vertical fence.
  • Continue pouring concrete perimeter at field enclosure two.
  • Start roof framing at enclosure two.

Recap of week ending November 18, 2021

  • Water storage tank finished.
  • Began stretching vertical fence at field enclosure one.
  • Continued concrete pour for field enclosure two perimeter.
  • Hauled and spread topsoil in field enclosure two.
  • Completed pulling vertical fencing at field enclosure two.
  • Lixit water rough in at field enclosure one ongoing.
  • Continued welding at field enclosure one.