TNPRC Breeding Colony Expansion - Week of November 12, 2021

Sources of Noise

  • Excavation equipment.
  • Hand Tools.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials and equipment.

Events for upcoming week

  • Continue pouring concrete perimeter at field enclosure two.
  • Haul and spread topsoil inside of field enclosure two.
  • Continue to pull and tie chain fence at field enclosure two.
  • Start roof framing at enclosure two.
  • Weld interior rails at field enclosure two.
  • Begin pulling fence at field enclosure one.
  • Lixit water installation at field enclosure one.
  • Tack weld horizonal rails at enclosure one.

Recap of week ending November 11, 2021

  • Began pouring and finishing enclosure two concrete perimeter.
  • Hauled and spread topsoil in field enclosure two.
  • Continued pulling fence at field enclosure two.
  • Lixit water rough in at field enclosure one.
  • Continued welding at field enclosure one.