Sources of Noise
- Work Vehicles
- Hand Tools
- Power Tools
Utility Shutdowns:
- None
Deliveries
- None Scheduled
Events for upcoming week
- Complete Q-Rail.
- Final adjustment on wood slat system.
- Millwork to receive final sealer.
- HRL Walk through to prepare Punch list.
- Install Camera
- Install TV
- Start Demobilization.
Recap of week performed (June 30 – July 07, 2019)
- Continue Q-Rail install.
- Start pre-final cleaning.
- Data completed.