Richardson Memorial - Week of September 23,2022

Sources of Noise

  • Heavy Equipment operations
  • Skid steer mounted jack hammer
  • Hand tools (Hammer drills, etc.)

Utility Shutdowns

  • None at this time

Deliveries 

  • 30yd dumpsters being swapped as needed to remove debris
  • Connex delivery 26 Sept 2022
  • General construction materials (supplies, lumber, ets)
  • Additional scaffolding

Events for upcoming week

  • Complete and clear 1st fl south abatement, then demo walls, ceilings, pipes
  • Abate 2 closet flooring areas of 1st Fl central and NE area
  • Abate SE ext window frames and paint
  • Drill beam pockets on NE exterior
  • Construct piling cages in prep for auger cast activity
  • Remove and store East lighting and add temp lighting
  • Demo old transformer vault pedestal in SE site corner

Recap of week ending Sept 21, 2022

  • Power Shutdown to make temp power connections
  • Complete beam pocket drilling on SE exterior and mount base plates
  • Demo old Transformer vault in SE site corner, add temp light for area
  • Clear 2nd Fl South abatement, demo walls, floors, and pipes
  • Demo 2nd Fl lobby ceiling
  • Begin 1st Fl S floor abatement
  • Connect temp fire alarm components to temp power panels
  • Mark beam pockets on NE exterior