Sources of Noise
- Heavy Equipment operations
- Skid steer mounted jack hammer
- Hand tools (Hammer drills, etc.)
Utility Shutdowns
- None at this time
Deliveries
- 30yd dumpsters being swapped as needed to remove debris
- Connex delivery 26 Sept 2022
- General construction materials (supplies, lumber, ets)
- Additional scaffolding
Events for upcoming week
- Complete and clear 1st fl south abatement, then demo walls, ceilings, pipes
- Abate 2 closet flooring areas of 1st Fl central and NE area
- Abate SE ext window frames and paint
- Drill beam pockets on NE exterior
- Construct piling cages in prep for auger cast activity
- Remove and store East lighting and add temp lighting
- Demo old transformer vault pedestal in SE site corner
Recap of week ending Sept 21, 2022
- Power Shutdown to make temp power connections
- Complete beam pocket drilling on SE exterior and mount base plates
- Demo old Transformer vault in SE site corner, add temp light for area
- Clear 2nd Fl South abatement, demo walls, floors, and pipes
- Demo 2nd Fl lobby ceiling
- Begin 1st Fl S floor abatement
- Connect temp fire alarm components to temp power panels
- Mark beam pockets on NE exterior