Richardson Memorial - Week of September 16,2022

Sources of Noise

  • Heavy Equipment
  • Auger Cast crane movement
  • Hand tools (Jack Hammers, Hammer drills, etc.)

Utility Shutdowns

  • Second Shutdown slated for 9/15/22, 10Am-4AM

Deliveries 

  • 30yd dumpsters being swapped as needed to remove debris
  • Piling rebar to be delivered 14th-15th Sept
  • Auger Cast crane delivery
  • Scaffolding for ext brick work

Events for upcoming week

  • Electrical Shutdown tonight @10PM
  • Add temp Lighting East side of Bldg
  • Continue drilling beam pockets and adding L bracket base plates
  • Demo 3rd Fl S Stairs
  • Demo 2nd Fl MEP, South floors, N walls and Floor
  • Debris removal
  • Demo Transformer Vault and swap Fire alarm power to temp power. 
  • Continue exploring Structural issues
  • Auger Cast delivery and assembly

Recap of week ending Sept 14, 2022

  • Power Shutdown to feed temp transformer
  • Demo elevator pit area and backfill with sand
  • Layout and drill Beam pockets for additions / verify base plate mounting
  • Abate 2nd Fl S / S Stair
  • Add temp power panels to interior and run cables to building switchgear.
  • Finish east window abatement
  • Continue structural assessment and safety improvements such as identifying hazardous subfloor areas and mark with danger tape and paint
  • Cover open windows