Sources of Noise
- Heavy Equipment
- Auger Cast crane movement
- Hand tools (Jack Hammers, Hammer drills, etc.)
Utility Shutdowns
- Second Shutdown slated for 9/15/22, 10Am-4AM
Deliveries
- 30yd dumpsters being swapped as needed to remove debris
- Piling rebar to be delivered 14th-15th Sept
- Auger Cast crane delivery
- Scaffolding for ext brick work
Events for upcoming week
- Electrical Shutdown tonight @10PM
- Add temp Lighting East side of Bldg
- Continue drilling beam pockets and adding L bracket base plates
- Demo 3rd Fl S Stairs
- Demo 2nd Fl MEP, South floors, N walls and Floor
- Debris removal
- Demo Transformer Vault and swap Fire alarm power to temp power.
- Continue exploring Structural issues
- Auger Cast delivery and assembly
Recap of week ending Sept 14, 2022
- Power Shutdown to feed temp transformer
- Demo elevator pit area and backfill with sand
- Layout and drill Beam pockets for additions / verify base plate mounting
- Abate 2nd Fl S / S Stair
- Add temp power panels to interior and run cables to building switchgear.
- Finish east window abatement
- Continue structural assessment and safety improvements such as identifying hazardous subfloor areas and mark with danger tape and paint
- Cover open windows