Richardson Hall 1st Floor Renovation- Week of September 18, 2020

Possible Sources of Noise

  • Tools
    • Saws
    • Grinders
    • Compressors
    • Nail Guns
    • Hammering
    • Fans
  • General jobsite noise
    • Delivery Trucks

Utility Shutdowns

  • None Scheduled

Deliveries/Pick-up

  • Framing materials
  • Misc job materials

Events for upcoming week

  • Continue structural work on 3rd floor
  • Contractor to continue electrical rough in
  • Contractor to complete demo of auditorium ceiling
  • Contractor to form & pour elevator pit

Weekend Work (Sat September 19, 2020)

  • None

Recap of week ending (September 19, 2020)

  • Contractor completed footings @ rear stairs & ADA ramp
  • Contractor prepped & secured site for hurricane
  • Continued electrical rough in
  • Continued installing floor boxes
  • Continued structural/steel work on 3rd floor
  • Contractor began work on elevator pit
  • Contractor continued demo of auditorium ceiling
  • Continued pulling new data wire
  • Continued sheetrock finishing on 2nd floor
  • Completed demo of footings @ elevator pit