Possible Sources of Noise
- Tools
- Saws
- Grinders
- Compressors
- Nail Guns
- Hammering
- Fans
- General jobsite noise
- Delivery Trucks
Utility Shutdowns
- None Scheduled
Deliveries/Pick-up
- Framing materials
- Misc job materials
Events for upcoming week
- Contractor to continue concrete work @ rear ADA ramp & stairs
- Contractor to continue electrical rough in
- Contractor to begin work @ auditorium ceiling
- Contractor to continue sprinkler installation
- Structural steel install for elevator to begin
Weekend Work (Sat. October 10, 2020)
- Sawcutting electrical floorboxes on 1st & 2nd floor
- Remove A/C units on roof of mechanical room
- Recap of week ending (October 10th, 2020)
- Contractor continued building forms for rear ADA ramp & stairs
- Contractor continued sheetrock @ 2nd floor corridor
- Continued electrical rough in
- Continued mechanical rough in
- Completed structural/steel work on 3rd floor
- Contractor began sprinkler material layout
- Continued sanding & priming on 1st & 2nd floor