Richardson Hall 1st Floor Renovation- Week of October 11, 2019

Possible Sources of Noise

  • Tools

    • Saws
    • Grinders
    • Compressors
    • Nail Guns
    • Hammering
    • Fans
    • General jobsite noise
  • Delivery Trucks

Utility Shutdowns

  • None Scheduled

Shutdowns

  • None

Deliveries/Pick-up

  • Framing materials
  • Plumbing Materials
  • Electrical Materials

Events for upcoming week

  • Plumbers to continue rough in
  • Electricians to continue rough in 
  • Mechanical sub to continue duct install

Weekend Work (Sat-Sun October 12-13 , 2019)

  • None

Recap of week ending (October 12, 2019)

  • Contractor completed demo of front entrance corridor
  • Contractor continued demo @ rear of classroom