Richardson Hall 1st Floor Renovation- Week of April 26, 2019

Possible Sources of Noise

  • Delivery Trucks
  • Contractor Trucks
  • Small Power Tools (Drills, saws etc.) 
  • Manual Tools (Hammers, pry bars, sledgehammer, etc.) 

Utility Shutdowns

  • None

Shutdowns

  • Toilet Rooms – Women’s Toilet Room ONLY was taken off line Wednesday April 24, 2019. Portable toilets are available at the North side of Richardson. A gender neutral toilet room is available on the 2nd floor of Richardson. Toilet rooms are also availible on the first floor of adjacent buildings, Stanley Thomas and Richardson Memorial. 
  • Bike Racks have been relocated directly across sidewalk

Deliveries/Pick-up

  • Misc Equipment 
  • Removal of demo debris (trailers will occupy parking spaces) 

Events for upcoming week

  • Contractor to continue demo on interior walls & framing
  • Contractor to continue removing existing mechanical connections
  • Contractor to continue demo of Women’s toilet room
  • Contractor to begin installing underlayment on 1st floor

Weekend Work ( Sat-Sun April 27-28 , 2019)

  • None

Recap of week ending (April 27, 2019)

  • Contractor continued 1st floor exploratory demo (quad side)
  • Contractor continued demo of interior walls & framing (quad and Engineers Rd side) 
  • Contractor continued removing misc existing mechanical conditions
  • Contractor evacuated refrigerant from existing HVAC units on 1st Floor