Richardson Hall 1st Floor Renovation- Week of April 12, 2019

Possible Sources of Noise

  • Delivery Trucks
  • Contractor Trucks
  • Small Power Tools (Drills, saws etc.) 
  • Manual Tools (Hammers, pry bars, sledgehammer, etc.) 

Utility Shutdowns

  • None

Shutdowns

  • Toilet rooms scheduled to come off line early March have been rescheduled until further notice.
  • Bike Racks have been relocated directly across sidewalk
  • Possible Steam/Chilled Water Shutdown between 4/16-4/18

Deliveries/Pick-up

  • Possible delivery of People Pleaser
  • Misc Equipment 
  • Removal of demo debris 

Events for upcoming week

  • Contractor to continue demo on interior walls & framing
  • Contractor to continue removing existing mechanical connections
  • Contractor to begin re-routing & connecting Chilled Water lines in crawl space

Weekend Work ( Sat-Sun April 13-14 , 2019)

  • None

Recap of week ending (April 13, 2019)

  • Contractor continued 1st floor exploratory demo
  • Contractor began demo of interior walls & framing
  • Contractor began removing misc existing mechanical conditions
  • Contractor began exploratory work for upcoming Chilled Water & Steam tie-ins