Possible Sources of Noise
- Delivery Trucks
- Contractor Trucks
- Small Power Tools (Drills, saws etc.)
- Manual Tools (Hammers, pry bars, sledgehammer, etc.)
Utility Shutdowns
- None
Shutdowns
- Toilet rooms scheduled to come off line early March have been rescheduled until further notice.
- Bike Racks have been relocated directly across sidewalk
- Possible Steam/Chilled Water Shutdown between 4/16-4/18
Deliveries/Pick-up
- Possible delivery of People Pleaser
- Misc Equipment
- Removal of demo debris
Events for upcoming week
- Contractor to continue demo on interior walls & framing
- Contractor to continue removing existing mechanical connections
- Contractor to begin re-routing & connecting Chilled Water lines in crawl space
Weekend Work ( Sat-Sun April 13-14 , 2019)
- None
Recap of week ending (April 13, 2019)
- Contractor continued 1st floor exploratory demo
- Contractor began demo of interior walls & framing
- Contractor began removing misc existing mechanical conditions
- Contractor began exploratory work for upcoming Chilled Water & Steam tie-ins