Paul Hall - Week of November 5, 2021

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • Re-feed A/C panel 225
  • Chiller disconnect swap

Deliveries

  • MEP utility equipment
  • Misc jobsite materials

Events for upcoming week

  • Continue load out of debris
  • Start heavy demo of Building 16
  • Install framing & steel @ Flower Hall connection
  • Wrap & roof mechanical doghouse on roof of Building 12
  • Development of the Paul Hall Project Documents continues. 
  • Installation of MEP utilities on the Building 12 roof continues. 
  • Heavy demolition of building 14 continues.
  • Demolition debris removal will continue
  • The installation and tie-in of new infrastructure items on the building 12 roof continues. 
  • Removal of the Flower Hall to Building 12 connector continues. 

Recap of week performed (October 31st- November 6th , 2021)

  • Relocated VRF unit to rooftop platform on Building 12
  • Temp shoring poles installed @ Makers Space
  • Continued demo @ connector
  • Continued rooftop platform work
  • Continued hauling out debris
  • Re-feed A/C panel 225-Saturday