Sources of Noise
- Heavy Equipment
- Demolition
- Utility Vehicles
- Power Tools
Utility Shutdowns:
- Re-feed A/C panel 225
- Chiller disconnect swap
Deliveries
- MEP utility equipment
- Misc jobsite materials
Events for upcoming week
- Continue load out of debris
- Start heavy demo of Building 16
- Install framing & steel @ Flower Hall connection
- Wrap & roof mechanical doghouse on roof of Building 12
- Development of the Paul Hall Project Documents continues.
- Installation of MEP utilities on the Building 12 roof continues.
- Heavy demolition of building 14 continues.
- Demolition debris removal will continue
- The installation and tie-in of new infrastructure items on the building 12 roof continues.
- Removal of the Flower Hall to Building 12 connector continues.
Recap of week performed (October 31st- November 6th , 2021)
- Relocated VRF unit to rooftop platform on Building 12
- Temp shoring poles installed @ Makers Space
- Continued demo @ connector
- Continued rooftop platform work
- Continued hauling out debris
- Re-feed A/C panel 225-Saturday