Paul Hall - Week of July 29, 2022

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • Deliveries
  • Job trailers
  • Misc jobsite materials
  • Misc equipment

Events for upcoming week

  • Development of the Paul Hall Project Documents continues
  • Continue structural steel
  • Continue mechanical rough in
  • Continue work on Chilled Water & Steam
  • Continue framing walls on 1st floor
  • Pour 4th floor deck 8/3

Recap of week performed (July 24th-July 30th  2022)

 

  • Completed temp walls in Flower Hall
  • Continued fireproofing 2nd floor steel
  • Continued overhead rough-in on 1st floor
  • Continued metal decking on 4th & 5th floor
  • Continued work on Chilled Water & Steam 
  • Continued framing walls on 1st floor