Paul Hall - Week of January 8, 2021

Sources of Noise

  • None

Utility Shutdowns:

  • None

Deliveries

  • None

Events for upcoming week

  • Move-out of building 14 continues. 
  • Project Document review and development continues.
  • End user meetings continue. 
  • Parking on Engineers Rd. is scheduled to be shutdown starting Jan 01 due to work associated with the future Paul Hall. 
  • Installation of a construction fence will begin during the week of Jan 10, 2021. 

Recap of week performed (Dec 03 – Jan 09, 2021)

  • Occupant move-out of Building 14 continues.
  • Project Document review and development is ongoing. 
  • End user meetings continue to occur. 
  • Parking on Engineers Rd. is scheduled to be shutdown starting Jan 01 due to work associated with the future Paul Hall.