Sources of Noise
- None
Utility Shutdowns:
- None
Deliveries
- None
Events for upcoming week
- Move-out of building 14 continues.
- Project Document review and development continues.
- End user meetings continue.
- Parking on Engineers Rd. is scheduled to be shutdown starting Jan 01 due to work associated with the future Paul Hall.
- Installation of a construction fence will begin during the week of Jan 10, 2021.
Recap of week performed (Dec 03 – Jan 09, 2021)
- Occupant move-out of Building 14 continues.
- Project Document review and development is ongoing.
- End user meetings continue to occur.
- Parking on Engineers Rd. is scheduled to be shutdown starting Jan 01 due to work associated with the future Paul Hall.