Paul Hall - Week of August 12, 2022

Sources of Noise

  • Heavy Equipment
  • Demolition
  • Utility Vehicles
  • Power Tools

Utility Shutdowns:

  • Deliveries
  • Job trailers
  • Misc jobsite materials
  • Misc equipment

Events for upcoming week

  • Development of the Paul Hall Project Documents continues
  • Continue structural steel
  • Continue mechanical rough in
  • Continue work on Chilled Water & Steam
  • Begin framing walls on 1st floor
  • Pour 5th floor deck 8/15

Recap of week performed (August 7th- August  13th  2022)

  • Continued fireproofing 3rd floor steel
  • Continued overhead rough-in on 1st &  2nd floor
  • Continued metal decking on 4th & 5th floor
  • Continued work on Chilled Water & Steam 
  • Continued framing walls on 1st & 2nd floors