Sources of Noise
- Power tools
- Hand tools
- Construction vehicles
Utility Shutdowns:
- None
Deliveries
- Dumpster
Events for upcoming week
- Gill will be complete with Phase One environmental remediation.
- WD Scott to provide final clearance.
- Contractor interviews may occur this week.
- Project Document development to continue.
Recap of week performed (April 04 – April 10, 2021)
- Gill Industries has received all clearances in building 16 and awaiting clearance on building 14.
- Phase One environmental clearance will be complete once the final clearance is received.
- WD Scott performing environmental oversight.
- Don’s Striping marked the Fire Lane on Engineering Rd.