Mussafer Hall - Week of March 4, 2018

Sources of Noise

  • Delivery Trucks
  • Heavy Equipment
  • Power Tools

Utility Shutdowns

  • Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined

Deliveries

  • Metal Panels, Roof Material, Windows, Lumber, Equipment

Events for upcoming week

  • Contractor to begin installing Storefront 
  • Interior to continue in existing building
  • Contractor to continue sheetrock install at addition
  • Work @ bay windows to continue
  • Roof work to continue
  • Contractor to continue ductwork @ new addition
  • Stucco & plaster work to continue
  • Electrical inspection to continue
  • Contractor to prep for chilled water connection
  • A/C to be powered up – 100% fresh air
  • Recap of week ending (March 3, 2018)

Contractor began prepping exterior for stucco 

  • Sheetrock install @ penthouse began
  • Contractor began work @ Stair 1 landing
  • Contractor began prepping for sewer tie in
  • Waterproofing @ terrace continues
  • High voltage testing continued
  • Contractor continued work @  Bay Windows
  • Contractor continued sheetrock at 2nd floor of  addition
  • Duct insulation continues @ New addition