Mussafer Hall - Week of March 4, 2018
Sources of Noise
- Delivery Trucks
- Heavy Equipment
- Power Tools
Utility Shutdowns
- Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined
Deliveries
- Metal Panels, Roof Material, Windows, Lumber, Equipment
Events for upcoming week
- Contractor to begin installing Storefront
- Interior to continue in existing building
- Contractor to continue sheetrock install at addition
- Work @ bay windows to continue
- Roof work to continue
- Contractor to continue ductwork @ new addition
- Stucco & plaster work to continue
- Electrical inspection to continue
- Contractor to prep for chilled water connection
- A/C to be powered up – 100% fresh air
- Recap of week ending (March 3, 2018)
Contractor began prepping exterior for stucco
- Sheetrock install @ penthouse began
- Contractor began work @ Stair 1 landing
- Contractor began prepping for sewer tie in
- Waterproofing @ terrace continues
- High voltage testing continued
- Contractor continued work @ Bay Windows
- Contractor continued sheetrock at 2nd floor of addition
- Duct insulation continues @ New addition