Mussafer Hall - Week of March 11, 2018

Sources of Noise

  • Delivery Trucks
  • Heavy Equipment
  • Power Tools

Utility Shutdowns

  • Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined

Deliveries

  • Metal Panels, Roof Material, Windows, Lumber, Equipment
  • Door Hardware

Events for upcoming week

  • Contractor to continue installing Storefront 
  • Sheetrock install at addition to continue
  • Work @ bay windows to wrap up
  • Roof work to continue
  • Contractor to continue duct insulation @ VAVs
  • Stucco & plaster work to continue 
  • A/C to be powered up – 100% fresh air
  • High Voltage work to wrap up

Recap of week ending (March 10, 2018)

  • Contractor began stucco on E side
  • Storefront install began @ 2nd & 3rd floor E side
  • Sheetrock install @ penthouse completed
  • Contractor completed work @ Stair 1 & landing
  • Contractor completed sewer tie in
  • Waterproofing continues
  • High voltage testing conti0
  • Contractor continued work @ final Bay Windows
  • Contractor continued sheetrock at 2nd floor of  addition
  • Duct insulation continues @ New addition