Mussafer Hall - Week of February 25, 2018

Sources of Noise

  • Delivery Trucks
  • Heavy Equipment
  • Power Tools

Utility Shutdowns

  • Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined

Deliveries

  • Metal Panels, Roof Material, Windows, Lumber, Equipment

Events for upcoming week    

  • Contractor to continue sheetrock install at addition
  • Work @ bay windows to continue
  • Roof work to continue
  • Contractor to continue ductwork @ new addition
  • Duct insulation to continue in attic of  existing building
  • Commissioning & electrical inspection to continue
  • Contractor to prep for chilled water connection
  • Temporary enclosures completed
  • A/C to be powered up – 100% fresh air

Recap of week ending (February 24, 2018)

  • Electrical rough in complete
  • High voltage testing began 2/22
  • Contractor continued work @  Bay Windows
  • Contractor began sheetrock at 2nd floor of new addition
  • Duct work continues @ New addition
  • Duct testing completed in attic of existing