Mussafer Hall - Week of February 25, 2018
Sources of Noise
- Delivery Trucks
- Heavy Equipment
- Power Tools
Utility Shutdowns
- Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined
Deliveries
- Metal Panels, Roof Material, Windows, Lumber, Equipment
Events for upcoming week
- Contractor to continue sheetrock install at addition
- Work @ bay windows to continue
- Roof work to continue
- Contractor to continue ductwork @ new addition
- Duct insulation to continue in attic of existing building
- Commissioning & electrical inspection to continue
- Contractor to prep for chilled water connection
- Temporary enclosures completed
- A/C to be powered up – 100% fresh air
Recap of week ending (February 24, 2018)
- Electrical rough in complete
- High voltage testing began 2/22
- Contractor continued work @ Bay Windows
- Contractor began sheetrock at 2nd floor of new addition
- Duct work continues @ New addition
- Duct testing completed in attic of existing