Mussafer Hall - Week of February 18, 2018

Sources of Noise

  • Delivery Trucks
  • Heavy Equipment
  • Power Tools

Utility Shutdowns

  • Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined

Deliveries

  • Metal Panels, Roof Material, Windows, Lumber, Equipment

Events for upcoming week

  • Electrical rough in to continue @ New addition. Tie into electrical room
  • Contractor to continue sheetrock install at addition
  • Work @ bay windows to continue
  • Roof work to continue
  • Contractor to build temporary enclosures for small storefront windows at connection 

Recap of week ending (February 17, 2018)

  • Contractor completed steam tie in at N. side
  • Contractor continued work @  Bay Windows
  • Contractor started sheetrock install at 3rd floor
  • Duct work continues @ New addition
  • Duct testing at attic of existing building 
  • Electrical closet and transformer set in place and wired
  • Roof work continues