Mussafer Hall - Week of February 18, 2018
Sources of Noise
- Delivery Trucks
- Heavy Equipment
- Power Tools
Utility Shutdowns
- Future electrical shut down to repair temp power pole to involve Alcee Fortier. To be Determined
Deliveries
- Metal Panels, Roof Material, Windows, Lumber, Equipment
Events for upcoming week
- Electrical rough in to continue @ New addition. Tie into electrical room
- Contractor to continue sheetrock install at addition
- Work @ bay windows to continue
- Roof work to continue
- Contractor to build temporary enclosures for small storefront windows at connection
Recap of week ending (February 17, 2018)
- Contractor completed steam tie in at N. side
- Contractor continued work @ Bay Windows
- Contractor started sheetrock install at 3rd floor
- Duct work continues @ New addition
- Duct testing at attic of existing building
- Electrical closet and transformer set in place and wired
- Roof work continues