Sources of Noise

  • Delivery Trucks
  • Heavy Equipment
  • Power Tools

Utility Shutdowns

  • Possible frequent, short-term road closures
  • Possible frequent, long-term road closures
  • Steam Shutdown 2/9 (final scheduled steam shutdown)

Deliveries

  • Steel, Lumber, Equipment

Events for upcoming week

  • Electrical & Plumbing rough in to continue @ New addition
  • Contractor to continue interior framing @ New addition
  • Work @ bay windows to continue
  • Roof work to continue
  • Waterproofing to continue @ new addition
  • Contractor to build temporary enclosures for storefront windows 

Recap of week ending (February 10, 2018)

  • Contractor completed chilled water work on N end of building
  • Contractor continued work @  Bay Windows
  • Interior wall framing continued @ New addition
  • Duct work continues @ New addition
  • Electrical & Plumbing continued @ New addition