Howard Tilton Memorial Library Basement Buildout - Week of October 9, 2020

Sources of Noise

  • Hand tools and power tools 
  • Work vehicles
  • Selective Demolition
  • Material Deliveries

Utility Shutdowns:

  • A domestic water shutdown is scheduled to occur on 10/14. 

Deliveries

  • None scheduled at this time. 

Events for upcoming week

  • The contractor will continue MEP layout and installation. 
  • Framing will continue.  
  • Drywall installation will continue. 
  • Mechanical duct work installation will commence in the ceiling of B18. 

Recap of week performed (Oct 04 – Oct 10, 2020)

  • HTE continues to rough-in electrical branch circuitry.    
  • MCC continues duct work fabrication and installation. Plumbing layout and installation continues. 
  • Donahue Favret completed the lift station room in the empty elevator pit.  
  • Framing layout and framing installation continues
  • Selective demolition is complete. 
  • Drywall installation has commenced.