Howard Tilton Memorial Library Basement Buildout - Week of January 8, 2021

Sources of Noise

  • Hand tools and power tools 
  • Work vehicles
  • Material Deliveries

Utility Shutdowns:

  • None

Deliveries

  • Furniture deliveries anticiapated

Events for upcoming week

  • The contractor will continue MEP trim-out. 
  • Final paint to continue.
  • Punch list walk through scheduled.
  • Flooring installation continues. 
  • Storefront installation continues. 
  • AV installation continues. 
  • Locker installation scheduled for this week. 
  • Bathroom partition installation will commence. 

Recap of week performed (Jan 03 – Jan 09, 2021).

  • Electrical, data, and fire alarm trim-out continues. 
  • HVAC trim-out continues.  
  • Plumbing trim-out continues. 
  • Final paint is underway.
  • Installation of fire sprinkler system complete.  
  • Ceiling grid and ceiling tile installation continues.   
  • Flooring installation continues. 
  • Storefront installation continues.   
  • Stair enclosure at stairwell #04 continues. 
  • Doors and door hardware are being installed.