Sources of Noise
- Hand tools and power tools
- Work vehicles
- Material Deliveries
Utility Shutdowns:
- None
Deliveries
- Furniture deliveries anticiapated
Events for upcoming week
- The contractor will continue MEP trim-out.
- Final paint to continue.
- Punch list walk through scheduled.
- Flooring installation continues.
- Storefront installation continues.
- AV installation continues.
- Locker installation scheduled for this week.
- Bathroom partition installation will commence.
Recap of week performed (Jan 03 – Jan 09, 2021).
- Electrical, data, and fire alarm trim-out continues.
- HVAC trim-out continues.
- Plumbing trim-out continues.
- Final paint is underway.
- Installation of fire sprinkler system complete.
- Ceiling grid and ceiling tile installation continues.
- Flooring installation continues.
- Storefront installation continues.
- Stair enclosure at stairwell #04 continues.
- Doors and door hardware are being installed.