Housing Quad Redevelopment- Week of September 23, 2022

Sources of Noise

  • Power tools
  • Chipping Hammer
  • Trucks 
  • Machines

Utility Shutdowns w/ excavation to begin:

  • Water:  
  • Power: 
  • Chilled 

 
Deliveries

  • N/A

Road Closures/Blockages

  • N/A

Approved Extended Work Hours

  • N/A

Events for upcoming week

  • Hanging sheetrock on all floors
  • Installing windows at bridges
  • Plumbing rough in on all floors
  • Electric rough in on all floors
  • Brick work on A1
  • Painting on all floors 
  • Installing flooring in B1 and B2
  • Trimming out rooms in B1 & B2

Recap of week ending September 24, 2022

  • Plumbing rough in on all floors
  • Electrical rough in on all floors
  • Hanging sheetrock on 5th, 6th, and 7th floors
  • Duct work on all floors
  • Floors in B1 and B2
  • Painting on 6th and 7th floors
  • Brick work on B2 south