Housing Quad Redevelopment- Week of November 5, 2021

Sources of Noise

  • Power tools
  • Chipping Hammer
  • Trucks 
  • Machines

Utility Shutdowns w/ excavation to begin:

  • Water:  
  • Power: 
  • Chilled 

 
Deliveries

  • N/A

Road Closures/Blockages

  • N/A

Approved Extended Work Hours

  • N/A

Events for upcoming week

  • Framing interior walls 4th & 5th floor
  • Forming and Pouring walls
  • Pouring B2 6th floor east side
  • Installing CHW on north side of site
  • Installing underground plumbing in A2
  • Plumbing rough in on 3rd and 4th floors

Recap of week ending November 6, 2021

  • Poured A1 east slab
  • Steel delivery
  • Plumbing rough in
  • Daily wall deliveries