Housing Quad Redevelopment- Week of June 11, 2021

Sources of Noise

  • Power tools
  • Chipping Hammer
  • Trucks 
  • Machines

Utility Shutdowns w/ excavation to begin:

  • Water:  
  • Power: 
  • Chilled 

  Deliveries

  • N/A

Road Closures/Blockages

  • N/A

Approved Extended Work Hours

  • N/A

Events for upcoming week

  • Forming and pouring Walls 
  • Working on Level 3
  • Forming and pouring columns daily
  • Tying re-steel
  • Pulling PT Cables

Recap of week ending June 12, 2021

  • Forming and pouring columns 
  • Rebar delivery
  • Installed temp fencing between Wall and Phelps.
  • Hauling sand