Goldring/Woldenberg Complex - Week of March 11, 2018
Sources of Noise
- Power tools
- Hand Tools
- Trucks
- Heavy Equipment
Utility Shutdowns w/ excavation to begin:
- American Sprinkler Company is scheduled to replace a 8” fire sprinkler shutoff valve, which may occur this week. This work may result in the temporary shutdown of a portion of the fire suppression system. We are awaiting a timeline from the contractor in order to schedule this work.
Deliveries
Events for upcoming week
- Broadmoor continues to complete punchlist items.
- Furniture deliveries are scheduled for this week.
- HTE will continue addressing electrical punchlist items.
Recap of week performed (March 3 – March 10, 2018)
- Broadmoor continues to work on punchlist items.
- HTE is addressing electrical punch list items.
- MCC is addressing mechanical punch list items.
- CPC continues to perform minor touch up paint throughout the building.
- RCI pruned vegetation that was effected by the previous freezing temperatures.