Utility Shutdowns w/ excavation to begin:

  • American Sprinkler Company is scheduled to replace a 8” fire sprinkler shutoff valve, which may occur this week. This work may result in the temporary shutdown of a portion of the fire suppression system. We are awaiting a timeline from the contractor in order to schedule this work. 

Deliveries

  • N/A

Events for upcoming week

  • Broadmoor continues to complete punchlist items. 
  • Furniture deliveries are scheduled for this week.  
  • HTE will continue addressing electrical punchlist items. 

Recap of week performed (March 3 – March 10, 2018)

  • Broadmoor continues to work on punchlist items. 
  • HTE is addressing electrical punch list items. 
  • MCC is addressing mechanical punch list items. 
  • CPC continues to perform minor touch up paint throughout the building.