Godring/Woldenberg Business Complex - Week of February 11, 2018
Sources of Noise
- Power tools
- Trucks
- Machines
Utility Shutdowns w/ excavation to begin:
- None anticipated at this time.
Deliveries
Road Closures/Blockages
- Weinman Drive will be closed from 02/14/2018 through 02/21/2018 for the removal of the mobile offices.
Events for upcoming week
- William Scotsman, the site trailer distributer, will commence demobilization of the mobile offices.
- Broadmoor continues to complete punchlist items.
- Testing and balancing of the heating and cooling systems is in progress.
Recap of week performed (February 04 – February 10, 2018)
- Broadmoor continues to work on punchlist items.
- Testing and balancing of the heating and cooling systems continues throughout the building.
- HTE is addressing electrical punch list items.
- Design Centrix is installing the video walls in the Gateway of the Business School.
- William Scotsman, the site trailer distributer, continued to prepare the mobile offices for demobilization.