Godring/Woldenberg Business Complex - Week of February 11, 2018

Sources of Noise

  • Power tools
  • Trucks 
  • Machines

Utility Shutdowns w/ excavation to begin:

  • None anticipated at this time. 

Deliveries

  • N/A

Road Closures/Blockages

  • Weinman Drive will be closed from 02/14/2018 through 02/21/2018 for the removal of the mobile offices. 

Events for upcoming week

  • William Scotsman, the site trailer distributer, will commence demobilization of the mobile offices. 
  • Broadmoor continues to complete punchlist items. 
  • Testing and balancing of the heating and cooling systems is in progress. 

Recap of week performed (February 04 – February 10, 2018)

  • Broadmoor continues to work on punchlist items. 
  • Testing and balancing of the heating and cooling systems continues throughout the building. 
  • HTE is addressing electrical punch list items. 
  • Design Centrix is installing the video walls in the Gateway of the Business School. 
  • William Scotsman, the site trailer distributer, continued to prepare the mobile offices for demobilization.