Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of March 11, 2018
Sources of Noise
- Hand Tools
- Power Tools
- Material Delivery
Equipment
Utility Shutdowns
- The contractor has notified the team that anticipated electrical work may temporarily disrupt power to certain areas within Gibson hall on 03/015/2018.
Deliveries
Events for upcoming week
- BNB will start the renovation of the conference room on 3/12/2018.
- Rocker Electric will perform work associated with the electrical branch circuitry on 3/15/2018.
Recap of work performed (March 4– March 10, 2018)
- The Contractor, BNB, has completed interior painting, installation of new doors, electrical work and carpet installation in Phase 4 of the Provost Suite Renovation.
- BNB has commenced reinstalling the previously moved furniture in Phase 4. This work is scheduled to be complete by 03/09/2018.