Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of March 11, 2018

Sources of Noise

  • Hand Tools
  • Power Tools
  • Material Delivery

Equipment

  • Hand Tools
  • Power Tools

Utility Shutdowns

  • The contractor has notified the team that anticipated electrical work may temporarily disrupt power to certain areas within Gibson hall on 03/015/2018.

Deliveries

  • Carpet

Events for upcoming week

  • BNB will start the renovation of the conference room on 3/12/2018.
  • Rocker Electric will perform work associated with the electrical branch circuitry on 3/15/2018. 

Recap of work performed (March 4– March 10, 2018) 

  • The Contractor, BNB, has completed interior painting, installation of new doors, electrical work and carpet installation in Phase 4 of the Provost Suite Renovation.  
  • BNB has commenced reinstalling the previously moved furniture in Phase 4. This work is scheduled to be complete by 03/09/2018.