Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of February 11, 2018

Sources of Noise

  • Hand Tools
  • Power Tools
  • Material Delivery
  • Equipment

Hand Tools

  • Power Tools

Utility Shutdowns

  • Electric disruption may occur this week. 

Deliveries

  • Carpet

Events for upcoming week

  • BNB will continue to prep and paint the interior walls and baseboard throughout Phase 3A of the project. 
  • O’Brian Flooring is scheduled to install sections of flooring.
  • Rocker is scheduled to switch receptacles in the work area. 

Recap of work performed (February 4 – February 10, 2018) 

  • The Contractor, BNB, completed the interior paint, and carpet installation in Phase 2A of the Provost renovation. 
  • BNB has commenced moving furniture out of Phase 3A of the Provost renovation. Wall prep, and carpet removal is scheduled to occur during this work period.