Gibson Hall Suite 200 – Provost Office Renovation and Carpet Replacement - Week of February 11, 2018
Sources of Noise
- Hand Tools
- Power Tools
- Material Delivery
- Equipment
Hand Tools
Utility Shutdowns
- Electric disruption may occur this week.
Deliveries
Events for upcoming week
- BNB will continue to prep and paint the interior walls and baseboard throughout Phase 3A of the project.
- O’Brian Flooring is scheduled to install sections of flooring.
- Rocker is scheduled to switch receptacles in the work area.
Recap of work performed (February 4 – February 10, 2018)
- The Contractor, BNB, completed the interior paint, and carpet installation in Phase 2A of the Provost renovation.
- BNB has commenced moving furniture out of Phase 3A of the Provost renovation. Wall prep, and carpet removal is scheduled to occur during this work period.