Gibson Financial Aid Renovation - Week of June 18, 2021

Sources of Noise

  • Power hand tools.

Utility Shutdowns

  • None at this time.

Deliveries 

  • Materials.

Events for upcoming week

  • Add glass to the operable partition rack.
  • Clean and polish Terrazzo floor.
  • Install bench fabric boards. 
  • Apply final finish to existing bricks.
  • Touch-up paint walls, ceiling, and trim.
  • Install glass for slider assemblies.  Caulk all joints.
  • Continue installing door hardware.
  • F1 light fixtures ongoing.
  • Install kitchenette sink.
  • Acquire State Fire Marshal substantial completion.

Recap of week ending June 17, 2021

  • Continued painting and touch ups.  
  • Benches and millwork finish has been applied.
  • Applied bonding primer to existing bricks.
  • Installed doors throughout the site.
  • Completed glass installation with the exception of the partition track.
  • Started installing F1 fixtures.  F4 and F5 lights complete.