The Commons - Week of September 9, 2018

Sources of Noise

  • None

Utility Shutdowns w/ excavation to begin:

  • Water: none
  • Power: none
  • Gas: none

Deliveries

  • Miscellaneous Deliveries

Road Closures/Blockages

  • N/A

Approved Extended Work Hours

  • Sat. 8am to 5pm
  • Sun. 9am to 5pm

Events for upcoming week

  • Preconstruction meeting for roofing
  • CW installation
  • Continue Fire proofing
  • Final roof concrete pour
  • Pour North plaza tie beams
  • Install temporary roof drains

Recap of week ending Sept. 8, 2018

  • Installing duct work
  • MEP rough in on 1st and 3rd 
  • Storm Prep
  • Wrecked forms at plaza walls
  • Crawl Space rough in
  • MEP rough in on 2nd and 3rd
  • Pour slab @ North plaza