Sources of Noise
- None
Utility Shutdowns w/ excavation to begin:
- Water: none
- Power: none
- Gas: none
Deliveries
- Miscellaneous Deliveries
Road Closures/Blockages
- N/A
Approved Extended Work Hours
- Sat. 8am to 5pm
- Sun. 9am to 5pm
Events for upcoming week
- Preconstruction meeting for roofing
- CW installation
- Continue Fire proofing
- Final roof concrete pour
- Pour North plaza tie beams
- Install temporary roof drains
Recap of week ending Sept. 8, 2018
- Installing duct work
- MEP rough in on 1st and 3rd
- Storm Prep
- Wrecked forms at plaza walls
- Crawl Space rough in
- MEP rough in on 2nd and 3rd
- Pour slab @ North plaza