The Commons - Week of January 3, 2020

Sources of Noise

  • None

Utility Shutdowns w/ excavation to begin:

  • Deliveries
  • Miscellaneous Deliveries

Road Closures/Blockages

  • N/A

Approved Extended Work Hours

  • Sat. 8am to 5pm
  • Sun. 9am to 5pm

Events for upcoming week

  • Execution of Punchlist throughout building
  • Durr Construction Installing Storm Water System

Recap of week ending January 4, 2020

  • Execution of Punchlist throughout building
  • Durr Construction Installing Storm Water System