Sources of Noise
- None
Utility Shutdowns w/ excavation to begin:
- Deliveries
- Miscellaneous Deliveries
Road Closures/Blockages
- N/A
Approved Extended Work Hours
- Sat. 8am to 5pm
- Sun. 9am to 5pm
Events for upcoming week
- Execution of Punchlist throughout building
- Durr Construction Installing Storm Water System
Recap of week ending January 4, 2020
- Execution of Punchlist throughout building
- Durr Construction Installing Storm Water System