The Commons - Week of January 10, 2020

Sources of Noise

  • None

Utility Shutdowns:

  • One electrical shutdown scheduled to occur next week. 

Road Closures/Blockages

  • N/A

Deliveries

  • Miscellaneous material deliveries 

Events for upcoming week

  • Execution of Punchlist throughout building continues. 
  • Concrete flat work is scheduled to be placed over the newly installed storm water retention system. 
  • Boh Bros is scheduled to install asphalt over the street cuts behind the LBC loading dock. 

Recap of week ending Jan 11, 2020

  • Execution of Punchlist throughout building.
  • Durr Construction completed the excavation and installation of the storm water retention system. 
  • Boh Bros excavated and repair damaged drain line. A liner was installed in one section of the drain line. 
  • All Star performing exterior electrical work. 
  • Work performed on the sump pump located in the LBC quad. 
  • BNB removed and replaced the emergency exit doors on the south side of the building.