Sources of Noise
- Hand Tools
- Power Tools
- Material Delivery
Equipment
- Hand Tools
- Power Tools
Utility Shutdowns
- None at this time
Deliveries
- Carpet
Events for upcoming week
- BNB will continue to reinstall the furniture in Phase 3.
- A Pre-construction conference is scheduled for Phase 4.
- BNB will remove the furniture from Phase 4, which will be temporarily stored in the Provost Conference Room. Interior paint prep will commence immediately following the removal of the furniture.
Recap of work performed (February 18 – February 24, 2018)
- The Contractor, BNB, has moved their efforts to Phase 3 of the project.
- BNB has completed interior paint in Phase 3. Carpet installation is scheduled to be completed this week.
- BNB will begin moving the furniture back into the Phase 3 offices.