The Commons - Week of April 12, 2019

Sources of Noise

  • None

Utility Shutdowns w/ excavation to begin:

  • Deliveries
  • Miscellaneous Deliveries

Road Closures/Blockages

  • N/A

Approved Extended Work Hours

  • Sat.  8am to 5pm
  • Sun. 9am to 5pm

Events for upcoming week

  • Continue terrazzo and resinous flooring
  • Continue installing Lighting 
  • Continue site work
  • Continue Vogl and ACT installation
  • Started on interior Glass walls
  • MEP trim out/Fixtures
  • Continue with CW & Glass Installation on West and South sides

Recap of weekending  April 13, 2019

  • TBES inspected Heat Exchanger
  • Continue terrazzo flooring
  • Continued Vogl and ACT installation
  • Glass Installation on Westside of build
  • Installed Linear diffusers
  • Complete elevator 3
  • Continue with CW & Glass Installation on West and South sides