Building 20 Autoclave- Week of April 2, 2021

Sources of Noise

  • None at this time.

Utility Shutdowns

  • None at this time.

Deliveries 

  • None at this time.

Events for upcoming week

  • Finalize design review of cage rack lifts.
  • Complete Getinge punch list items. 

Recap of week ending March 25, 2020.

  • Floor mounted both control boxes. 
  • Added steam trap.
  • Began floor penetrations for Getinge pop off valves.
  • Continued working on items noted by Commission Agent.