Bruff Demolition - Week of January 17, 2020

Sources of Noise

  • Hand Tools
  • Power Tools
  • Work Vehicles
  • Heavy Equipment

Utility Shutdowns:

  • Utilities will be cut off to the building as the demolition progresses. 

Deliveries

  • Demolition Equipment
  • Events for upcoming week
  • Insul-Tech continues interior and exterior building demolition. 
  • Demolition debris will continue to be hauled from site. 

Recap of week performed (Jan 12, 2020 – Jan 18, 2020)

  • Roofing material demolition is complete. 
  • Interior and exterior building demolition continues. 
  • Rocker Electric installed site lighting. 
  • Demolition debris continues to be removed from site. 
  • Underground utility termination continues.