Weinmann Roof Repair - Week of March 8, 2024

Sources of Noise

  • Power tools
  • Hand tools

Utility Shutdowns:

  • None

Deliveries

  • Dumpsters
  • Cranes and support trailers

Events for upcoming week

  • Continue commission of AHU-1,3 & 4
  • Crane lifts moving temporary air handlers from west roof to center roof
  • Continue finishing work on east roof: PMMA application and parapet caps
  • Connect temporary air handler units to AHU-5
  • Tuckpoint work on east wall of penthouse
  • SS cap work on AHU-2 and AHU-5 duct work

Recap of work performed (February 27 – March 4, 2024)

  • Start PMMA work on east roof
  • Continue AHU-3 & 4 commissioning
  • Start AHU-1 commissioning
  • SS cap work on AHU-2 and AHU-5 duct work
  • Continue tuckpointing the east wall of the penthouse