Weinmann Roof Repair - Week of March 29, 2024

Sources of Noise

  • Power tools
  • Hand tools

Utility Shutdowns:

  • None

Deliveries

  • Roofing materials

Events for upcoming week

  • Crane lift on Tuesday or Wednesday to fly materials to center roof 
  • Continue AHU-5 rehabilitation
  • Continue parapet cap work on east roof
  • Tuckpoint work on east wall of penthouse and east roof
  • SS cap work on AHU-2 and AHU-5 ductwork

Recap of work performed (March 19 - 25, 2024)

  • Rehabilitation of AHU-5 and AHU-2
  • Continue tuckpoint work on east roof of the penthouse, start east roof
  • Control lines run by Powers
  • Rehabilitation inside of AHU-5 supply and return ducts