Weinmann Roof Repair - Week of March 1, 2024

Sources of Noise

  • Power tools
  • Hand tools
  • Pressure washer
  • East roof demolition

Utility Shutdowns:

  • Smoke detectors on Tuesday, February 27
  • Deliveries
  • Dumpsters
  • Cranes and support trailers

Events for upcoming week

  • Complete commission of AHU-3, 4
  • Crane lifts moving temporary air handlers from west roof to center roof
  • Continue installation of top layer of east roof
  • Commission AHU-1
  • Connect temporary air handler units to AHU-5

Recap of work performed (February 20 - 26, 2024)

  • Continue east roof deck demo and reset
  • Continue AHU-3 & 4 commissioning
  • Continue AHU-1 rehab work
  • SS cap work on AHU-2 and AHU-5 duct work