Sources of Noise
- Power tools
- Hand tools
- Pressure washer
- East roof demolition
Utility Shutdowns:
- Smoke detectors on Tuesday, February 27
- Deliveries
- Dumpsters
- Cranes and support trailers
Events for upcoming week
- Complete commission of AHU-3, 4
- Crane lifts moving temporary air handlers from west roof to center roof
- Continue installation of top layer of east roof
- Commission AHU-1
- Connect temporary air handler units to AHU-5
Recap of work performed (February 20 - 26, 2024)
- Continue east roof deck demo and reset
- Continue AHU-3 & 4 commissioning
- Continue AHU-1 rehab work
- SS cap work on AHU-2 and AHU-5 duct work