Weinmann Roof Repair - Week of April 5, 2024

Sources of Noise

  • Power tools
  • Hand tools

Utility Shutdowns:

  • Smoke Detector shutdown on Wednesday, 4/3

Deliveries

  • None

Events for upcoming week

  • Continue AHU-2 and AHU-5 rehabilitation
  • Continue parapet cap work on east roof
  • Tuckpoint work on east wall of penthouse and east roof
  • SS cap work on AHU-2 and AHU-5 ductwork

Recap of work performed (March 26 – April 1, 2024)

  • Rehabilitation of AHU-2 and AHU-5
  • Paint AHU-2 and AHU-5
  • Continue tuckpoint work on east roof of the penthouse and east roof
  • Start insulation work inside AHU-5