Sources of Noise
- Hand Tools.
- Small Excavator.
Utility Shutdowns
- None at this time.
Deliveries
- Materials.
Events for upcoming week
- Continue hanging interior lights.
- Install main feed electrical panel.
- Continue metal trim.
- Complete corner detail waterproofing.
- Begin hanging siding following Architects waterproofing approval.
- Continue routing refrigerant lines.
- Plan sewer and domestic water tie in.
Recap of week ending March 22, 2024
- Began routing refrigerant lines.
- Waterproofed exhaust penetrations.
- Placed AC compressors on concrete pad.
- Removed canopy concrete forms, filled with sand, and compacted.